I am planning a manual assembly line for a small gearbox. The shift is 8 hours with 30 minutes of breaks, and the customer needs 360 units per shift. The assembly is split into 9 tasks whose times add up to 410 seconds, the longest single task being 62 seconds.
How do I get from these figures to a takt time and a number of workstations? I also see "cycle time" and "takt time" used as if they were the same thing, and I am not sure they are.