I have been asked to report OEE for a packaging machine. For one shift I have: 480 minutes shift length, 30 minutes of planned breaks, 45 minutes of breakdowns and changeover, an ideal cycle time of 0.5 minutes per unit, 700 units produced and 20 of them rejected.
How are the three factors calculated from these, where do changeovers and breaks belong, and what does it mean if my performance figure comes out above 100 percent on some shifts?